SAMPLE. Three source-backed historical records from the section's committed fixtures, rendered through the real product code so you can see what a reviewed record, a timeline, the weekly brief and the exports look like. Nothing here is live coverage: these records are not counted on the coverage page, were not published through review, and are not emailed. Every document behind them is a real municipal file, hashed and cited.

Data Centers — sample records

Westlake, TX — Circle T data center (2024–2026)

5 records, 15 hashed source documents. Westlake, TX — Circle T Data Center Campus. Source-backed, historical_backfill fixture for the Data Center section (Z-DC-18 / I-02). Preserved 2026-09-09 by the source-review session; raw documents and per-page text live outside the repo (data/sources/westlake-2026-09-09). Verify by re-fetching a URL and comparing sha256. Not a live lead: nothing after 2026-08-18 is known.

As the weekly brief lists them

Reporting period: 2026-09-09 to 2026-09-09. 1 project with newly observed or changed records (5 records) in this period.

Coverage: UNVERIFIED — prototype fixtures only; no live monitoring occurred.

  • SAMPLE: fixture records rendered for inspection; not a live reporting window

Executive summary

  • Circle T Data Center Campus (Westlake) — new track: development_agreement tabled (2026-08-17) — Westlake Town Council (special meeting) — tabled after a Tarrant County judge's temporary hold; next: A Tarrant County judge is expected to hear the matter at a hearing set for 10 am on August 26th 2026-08-26 (past)

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Circle T Data Center Campus

2026-08-17 — Westlake Town Council (special meeting) — tabled after a Tarrant County judge's temporary hold · Westlake, Tarrant County (first observed by us 2026-09-09)

What changed

new track: development_agreement tabled (2026-08-17). uncertain — Westlake Town Council (special meeting) — tabled after a Tarrant County judge's temporary hold, 2026-08-17; 23 days since this action

Why it matters

  • litigation — a Tarrant County judge put a temporary hold on the project. Because of the court order, the Town Council cannot act on the agreement at this time source, News flash 825, paragraphs 1-2
  • entitlement step — The Office of the Town Manager recommends approval of the development agreement as presented source, p.5
  • conditions — The development agreement --- and the ability of the Developer to receive a certificate of occupancy to operate the data center are predicated upon the Developer's compliance with the directive from the Governor concerning the comprehensive data center audit process that ... will be performed by the Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT) source, pp.3-4
  • conditions — In the event that the Developer is unable to receive the appropriate documentation from the PUCT and ERCOT ... the Town Manager may request that the Developer repurpose the buildings on the site for another land use source, p.4
  • water — cooling system designed to achieve an annual water usage effectiveness (WUE) not to exceed 0.25L/kWh as a long-term average source, p.4
  • conditions — heightened mitigation efforts for noise reduction ... acoustic louvers, berms, and sound barrier walls ... a report within 180 days following the completion of construction that demonstrates that the development is compliant with the Town's Code of Ordinances regulating noise source, p.4
  • One-time financial contribution — a one-time financial contribution to the Town in an amount not to exceed $914,000.00 to upgrade piping at the pump station ... to be paid to the Town within 30 calendar days of the execution of the development agreement source, pp.4-5
  • schedule — no grading activities will be allowed to commence unless and until the grading plans and drainage plans have been reviewed and approved by the Town Engineer source, p.4

Resolution 26-25 would approve a Development Agreement for Subdivision Improvements between the Town and Circle T Owner, LP: one-time contribution up to $914,000 for pump-station piping (due within 30 days of execution); cooling system WUE not to exceed 0.25 L/kWh long-term average; acoustic louvers, berms and sound walls plus a noise-compliance report within 180 days of construction completion; PUCT/ERCOT audit documentation under the Governor's 2026-08-03 directive required before a final certificate of occupancy, failing which the Town Manager may require the buildings be repurposed; no grading until Town Engineer approves grading/drainage plans. Council unanimously TABLED it because a Tarrant County judge placed a temporary hold; a court hearing was set for 10 am 2026-08-26 and a vote was to be scheduled afterwards.

Who should act

  • Investors / lenders / analysts / Developers / site selectors / Public affairs / community: a Tarrant County judge put a temporary hold on the project. Because of the court order, the Town Council cannot act on the agreement at this time (derived from a stated litigation factor) source
  • Developers / site selectors / Investors / lenders / analysts: The Office of the Town Manager recommends approval of the development agreement as presented (derived from a stated entitlement step factor) source
  • Investors / lenders / analysts / Utilities / infrastructure: The development agreement --- and the ability of the Developer to receive a certificate of occupancy to operate the data center are predicated upon the Developer's compliance with the directive from the Governor concerning the comprehensive data center audit process that ... will be performed by the Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT) (derived from a stated conditions factor) source
  • Investors / lenders / analysts: In the event that the Developer is unable to receive the appropriate documentation from the PUCT and ERCOT ... the Town Manager may request that the Developer repurpose the buildings on the site for another land use (derived from a stated conditions factor) source
  • Utilities / infrastructure / Equipment / construction suppliers / Public affairs / community: cooling system designed to achieve an annual water usage effectiveness (WUE) not to exceed 0.25L/kWh as a long-term average (derived from a stated water factor) source
  • Equipment / construction suppliers / Public affairs / community: heightened mitigation efforts for noise reduction ... acoustic louvers, berms, and sound barrier walls ... a report within 180 days following the completion of construction that demonstrates that the development is compliant with the Town's Code of Ordinances regulating noise (derived from a stated conditions factor) source
  • Investors / lenders / analysts / Utilities / infrastructure: a one-time financial contribution to the Town in an amount not to exceed $914,000.00 to upgrade piping at the pump station ... to be paid to the Town within 30 calendar days of the execution of the development agreement (derived from a stated other factor) source
  • Equipment / construction suppliers: no grading activities will be allowed to commence unless and until the grading plans and drainage plans have been reviewed and approved by the Town Engineer (derived from a stated schedule factor) source

What to do next

  • Look up: A Tarrant County judge is expected to hear the matter at a hearing set for 10 am on August 26th — Tarrant County district court, 2026-08-26 (past — outcome not in the sources) source
  • Monitor: Afterward, the Town will schedule a meeting to vote on the development agreement — Westlake Town Council [development agreement], date not stated (expected) source

Sources

Outcome: https://www.westlake-tx.org/m/newsflash/Home/Detail/825 — News flash 825 (whole): 'unanimously voted to table … after a Tarrant County judge put a temporary hold'; hearing 2026-08-26 10 am; Packet: https://westlaketx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=5484,plainText=false) — Item E.1 pp.3–8: Resolution 26-25 and staff report (Town Manager recommends approval); agreement terms; Corroboration: https://www.westlake-tx.org/m/newsflash/Home/Detail/824 — News flash 824: special meeting noticed for 2026-08-17 4:00 pm

Our analysis

Lifecycle: agreement pending

how this was derived

1 undated published record(s) not placed in time

text_amendment: approved (2025-01-06)

site_plan: approved (2026-08-04)

development_agreement: tabled (2026-08-17)

Momentum: stalled

how this was derived

1 undated published record(s) not placed in time

2026-08-04 site_plan: approved

2026-08-17 development_agreement: tabled

latest action tabled stalls

thresholds (provisional): advancing ≤ 90 d, stalled after 180 d, lookback 365 d

Stated risk: stated

how this was derived

litigation (stated, impedes): a Tarrant County judge put a temporary hold on the project. Because of the court order, the Town Council cannot act on the agreement at this time

entitlement_step (stated, advances): The Office of the Town Manager recommends approval of the development agreement as presented

conditions (stated, impedes): The development agreement --- and the ability of the Developer to receive a certificate of occupancy to operate the data center are predicated upon the Developer's compliance with the directive from the Governor concerning the comprehensive data center audit process that ... will be performed by the Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT)

conditions (stated, impedes): In the event that the Developer is unable to receive the appropriate documentation from the PUCT and ERCOT ... the Town Manager may request that the Developer repurpose the buildings on the site for another land use

water (stated, neutral): cooling system designed to achieve an annual water usage effectiveness (WUE) not to exceed 0.25L/kWh as a long-term average

conditions (stated, neutral): heightened mitigation efforts for noise reduction ... acoustic louvers, berms, and sound barrier walls ... a report within 180 days following the completion of construction that demonstrates that the development is compliant with the Town's Code of Ordinances regulating noise

other (stated, neutral): a one-time financial contribution to the Town in an amount not to exceed $914,000.00 to upgrade piping at the pump station ... to be paid to the Town within 30 calendar days of the execution of the development agreement

schedule (stated, neutral): no grading activities will be allowed to commence unless and until the grading plans and drainage plans have been reviewed and approved by the Town Engineer

Evidence grade: A (A: an outcome source; B: packet or agenda only; C: corroboration only)

Still unknown

  • site-plan application/case number (not in packet text)
  • IT load / critical capacity in MW (only 300 MW utility capacity and a 350 MW substation are stated)
  • tenant identity
  • outcome of the 2026-08-26 Tarrant County hearing, the cause number and the plaintiff
  • whether the development agreement has since been voted on (nothing after 2026-08-18 found)
  • P&Z 2026-08-04 minutes (not yet published on CivicClerk at retrieval time)
  • council vote count on Ordinance 1015 (2025-01-06 minutes are a scanned image; OCR not run)
  • the applicant for the 2024–25 PD 3-8 text amendment (unnamed in the packet text)
  • equipment vendors / supplier selection (only Ameristar Palisade fence and Lueders stone, presentation pp.18–22)
  • Separate track from seq 4: tabling the agreement does not undo the site-plan approval; conversely no building or grading permit can issue until the agreement is approved (P&Z packet p.41–42).
  • The August 26 hearing's outcome, cause number and plaintiff are in no preserved document. CivicClerk shows no council event between 2026-08-18 and 2026-09-01 other than the 08-25 Board of Trustees; the 2026-08-18 regular-meeting recap (826) has no data-center item.
  • Status as of 2026-09-09 is unknown from these sources.

Timeline

5 records of this project in the period; the current state above is the latest.

  1. Unknown — proposal — Town of Westlake / City of Keller / Hillwood Properties (pre-application meeting)
  2. 2024-12-10 — proposal — Westlake Planning & Zoning Commission (recommendation only, 5-1-1 with one absence)
  3. 2025-01-06 — approved — Westlake Town Council — Ordinance No. 1015 adopted after public hearing (File # ORD-1015, agenda item F.2)
  4. 2026-08-04 — approved — Westlake Planning & Zoning Commission (site plan, with three added conditions)
  5. 2026-08-17 — uncertain — Westlake Town Council (special meeting) — tabled after a Tarrant County judge's temporary hold (current)

Timeline

  1. undated — proposal · Town of Westlake / City of Keller / Hillwood Properties (pre-application meeting) · record
  2. 2024-12-10 — proposal · Westlake Planning & Zoning Commission (recommendation only, 5-1-1 with one absence) · record
  3. 2025-01-06 — approved · Westlake Town Council — Ordinance No. 1015 adopted after public hearing (File # ORD-1015, agenda item F.2) · record
  4. 2026-08-04 — approved · Westlake Planning & Zoning Commission (site plan, with three added conditions) · record
  5. 2026-08-17 — uncertain · Westlake Town Council (special meeting) — tabled after a Tarrant County judge's temporary hold · record

Evidence cards

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Circle T Data Center Campus — Circle T Ranch

MunicipalityWestlake
CountyTarrant
Address / locationNortheast corner of US Highway 377 and Westport Parkway, Westlake, TX (PD 3-8, Office/Industrial Sub-District); developer's deck gives 13572 N Main Street, Westlake, TX 76262
DeveloperUnknown
ApplicantUnknown
OwnerUnknown
Source published2026-08-01
Meeting dateUnknown
First observed by us2026-09-09
Stageproposal
Reviewing body (not a final decision)Town of Westlake / City of Keller / Hillwood Properties (pre-application meeting)
IT load (MW)Unknown
Stated capacity figuresUnknown
EquipmentUnknown
ApprovalsIn December 2024 Westlake, Keller and Hillwood leaders met to discuss the proposed development, including a preliminary site plan, location, size, noise, water and electrical infrastructure.
Supplier selectionUnknown

Source: https://www.westlake-tx.org/m/newsflash/Home/Detail/821 — News flash 821, paragraphs 2–3

Not yet established:

  • meeting date known only to 2024-12 precision (source: News flash 821, paragraphs 2–3)
  • site-plan application/case number (not in packet text)
  • IT load / critical capacity in MW (only 300 MW utility capacity and a 350 MW substation are stated)
  • tenant identity
  • outcome of the 2026-08-26 Tarrant County hearing, the cause number and the plaintiff
  • whether the development agreement has since been voted on (nothing after 2026-08-18 found)
  • P&Z 2026-08-04 minutes (not yet published on CivicClerk at retrieval time)
  • council vote count on Ordinance 1015 (2025-01-06 minutes are a scanned image; OCR not run)
  • the applicant for the 2024–25 PD 3-8 text amendment (unnamed in the packet text)
  • equipment vendors / supplier selection (only Ameristar Palisade fence and Lueders stone, presentation pp.18–22)
  • Month precision only.
  • A pre-application meeting, not a filing; the earliest dated event the Town itself cites.

Our review

Review stateneeds_review

Inference

Unknown

Why it matters

  • conditions — Westlake committed to working with the developer to: position the facility as far north on the property as possible, exceeding the planned development's required setback; ensure the facility complies with Westlake's noise ordinance; require extensive landscape screening, including mature vegetation source, News flash 821, paragraph 4
  • opposition — some concerns have been raised by residents in the City of Keller due to the project's proximity to the Keller city limits source, News flash 821, paragraph 1
  • support from Keller's leadership team — At the conclusion of that meeting, the project was met with support from Keller's leadership team, which expressed the belief that the development would have minimal impact on Keller residents source, News flash 821, paragraph 5

In December 2024 Westlake, Keller and Hillwood leaders met to discuss the proposed development, including a preliminary site plan, location, size, noise, water and electrical infrastructure.

Who should act

  • Developers / site selectors / Public affairs / community: Westlake committed to working with the developer to: position the facility as far north on the property as possible, exceeding the planned development's required setback; ensure the facility complies with Westlake's noise ordinance; require extensive landscape screening, including mature vegetation (derived from a stated conditions factor) source
  • Public affairs / community: some concerns have been raised by residents in the City of Keller due to the project's proximity to the Keller city limits (derived from a stated opposition factor) source
  • Public affairs / community: At the conclusion of that meeting, the project was met with support from Keller's leadership team, which expressed the belief that the development would have minimal impact on Keller residents (derived from a stated other factor) source

What to do next

no dated next step in the sources

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Circle T Data Center Campus — Circle T Ranch

MunicipalityWestlake
CountyTarrant
Address / locationNortheast corner of US Highway 377 and Westport Parkway, Westlake, TX (PD 3-8, Office/Industrial Sub-District); developer's deck gives 13572 N Main Street, Westlake, TX 76262
DeveloperUnknown
ApplicantUnknown
OwnerUnknown
Source publishedUnknown
Meeting date2024-12-10
First observed by us2026-09-09
Stageproposal
Reviewing body (not a final decision)Westlake Planning & Zoning Commission (recommendation only, 5-1-1 with one absence)
IT load (MW)Unknown
Stated capacity figuresUnknown
EquipmentUnknown
ApprovalsP&Z recommended approval of the PD 3-8 text amendments (which add 'Data Center — permitted by right in the Office/Industrial sub-area and by SUP in the Office sub-area', and 'Electrical Substations — permitted by right in the Office and Office/Industrial sub-areas instead of by SUP').
Supplier selectionUnknown

Source: https://westlaketx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=62,plainText=false) — p.36 (staff report, P&Z recommendation paragraph); p.81 (ordinance recital)

Not yet established:

  • site-plan application/case number (not in packet text)
  • IT load / critical capacity in MW (only 300 MW utility capacity and a 350 MW substation are stated)
  • tenant identity
  • outcome of the 2026-08-26 Tarrant County hearing, the cause number and the plaintiff
  • whether the development agreement has since been voted on (nothing after 2026-08-18 found)
  • P&Z 2026-08-04 minutes (not yet published on CivicClerk at retrieval time)
  • council vote count on Ordinance 1015 (2025-01-06 minutes are a scanned image; OCR not run)
  • the applicant for the 2024–25 PD 3-8 text amendment (unnamed in the packet text)
  • equipment vendors / supplier selection (only Ameristar Palisade fence and Lueders stone, presentation pp.18–22)
  • A recommendation, not a decision (regression c). The applicant for the text amendment is referred to only as 'the applicant'/'the developer' in the packet text; not named.

Our review

Review stateneeds_review

Inference

Unknown

Why it matters

  • entitlement step — Data Center --- to be permitted by right in the Office/Industrial sub-area and by an SUP in the Office sub-area source, p.33
  • capacity power — Electrical Substations --- to be permitted by right in the Office and Office/Industrial sub-areas instead of by Specific Use Permit source, p.33
  • entitlement step — a formal site plan submittal would still be required to be submitted that would proceed to the Planning and Zoning Commission for recommendation and subsequent consideration by the Town Council source, p.33
  • conditions — staff condition 1: After site plans have been submitted for the first data center in the Office / Industrial Sub-district for review and approval; each successive data center thereafter shall require a SUP source, p.35
  • conditions — staff condition 2: for the first data center in the Office/Industrial Sub-district only, the exterior finish material requirements and other architectural features contained in the building quality manual only apply to the building facades facing United States Highway 377 and residential properties source, p.35

P&Z recommended approval of the PD 3-8 text amendments (which add 'Data Center — permitted by right in the Office/Industrial sub-area and by SUP in the Office sub-area', and 'Electrical Substations — permitted by right in the Office and Office/Industrial sub-areas instead of by SUP').

Who should act

  • Developers / site selectors: Data Center --- to be permitted by right in the Office/Industrial sub-area and by an SUP in the Office sub-area (derived from a stated entitlement step factor) source
  • Utilities / infrastructure: Electrical Substations --- to be permitted by right in the Office and Office/Industrial sub-areas instead of by Specific Use Permit (derived from a stated capacity power factor) source
  • Developers / site selectors / Investors / lenders / analysts: a formal site plan submittal would still be required to be submitted that would proceed to the Planning and Zoning Commission for recommendation and subsequent consideration by the Town Council (derived from a stated entitlement step factor) source
  • Developers / site selectors: staff condition 1: After site plans have been submitted for the first data center in the Office / Industrial Sub-district for review and approval; each successive data center thereafter shall require a SUP (derived from a stated conditions factor) source
  • Developers / site selectors / Equipment / construction suppliers: staff condition 2: for the first data center in the Office/Industrial Sub-district only, the exterior finish material requirements and other architectural features contained in the building quality manual only apply to the building facades facing United States Highway 377 and residential properties (derived from a stated conditions factor) source

What to do next

  • Monitor: Hold a public hearing, discuss, consider and act to adopt Ordinance 1015 approving text amendments to PD 3-8 (File # ORD-1015, agenda item F.2) — Westlake Town Council [text amendment], 2025-01-06 (scheduled) source

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Circle T Data Center Campus — Circle T Ranch

MunicipalityWestlake
CountyTarrant
Address / locationNortheast corner of US Highway 377 and Westport Parkway, Westlake, TX (PD 3-8, Office/Industrial Sub-District); developer's deck gives 13572 N Main Street, Westlake, TX 76262
DeveloperUnknown
ApplicantUnknown
OwnerUnknown
Source publishedUnknown
Meeting date2025-01-06
First observed by us2026-09-09
Stageapproved
Decided byWestlake Town Council — Ordinance No. 1015 adopted after public hearing (File # ORD-1015, agenda item F.2)
IT load (MW)Unknown
Stated capacity figuresUnknown
EquipmentUnknown
ApprovalsText amendments to PD 3-8 ('generally located at the southeast corner of U.S. Highway 377 and State Highway 170'; Circle T Ranch, Ordinances 307/314 of 1998-09-14, 322 of 1998-12-14, 438 of 2003-06-09, 592 of 2008-04-24). Staff recommended approval with seven conditions, including the note that after the FIRST data center's site plan in the Office/Industrial Sub-district each successive data center requires an SUP, and that the building-quality-manual façade rules apply only to façades facing US 377 and residential properties for that first data center. Also raises Office/Industrial max height to 80 ft and lot coverage to 70%.
Supplier selectionUnknown

Source: https://westlaketx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=5474,plainText=false) — p.40 (Background: adoption of Ordinance 1015 on 2025-01-06); proposal text in council packet fileId 62 pp.32–36, 81–85

Not yet established:

  • site-plan application/case number (not in packet text)
  • IT load / critical capacity in MW (only 300 MW utility capacity and a 350 MW substation are stated)
  • tenant identity
  • outcome of the 2026-08-26 Tarrant County hearing, the cause number and the plaintiff
  • whether the development agreement has since been voted on (nothing after 2026-08-18 found)
  • P&Z 2026-08-04 minutes (not yet published on CivicClerk at retrieval time)
  • council vote count on Ordinance 1015 (2025-01-06 minutes are a scanned image; OCR not run)
  • the applicant for the 2024–25 PD 3-8 text amendment (unnamed in the packet text)
  • equipment vendors / supplier selection (only Ameristar Palisade fence and Lueders stone, presentation pp.18–22)
  • The council vote count is in the 2025-01-06 minutes (fileId 93), which are image-only (0 extractable characters) — not read. Adoption is established by the later staff report and resolution, not by minutes text.
  • The use approval is a separate track from the 2026 site plan.

Our review

Review stateneeds_review

Inference

Unknown

Why it matters

  • entitlement step — a data center is allowed by-right within the Office / Industrial Sub-District source, p.40
  • conditions — after site plans have been submitted for the first data center in the Office / Industrial Sub-district for review and approval, that each successive data center thereafter shall require a specific use permit source, p.40
  • entitlement step — site plan approval (subject to review and approval by the Planning and Zoning Commission) is required prior to the issuance of development permits and building permits source, p.41
  • entitlement step — a development agreement is also required ... grading permits and building permits may not be issued until the development agreement has been reviewed and approved by the Town Council source, p.41

Text amendments to PD 3-8 ('generally located at the southeast corner of U.S. Highway 377 and State Highway 170'; Circle T Ranch, Ordinances 307/314 of 1998-09-14, 322 of 1998-12-14, 438 of 2003-06-09, 592 of 2008-04-24). Staff recommended approval with seven conditions, including the note that after the FIRST data center's site plan in the Office/Industrial Sub-district each successive data center requires an SUP, and that the building-quality-manual façade rules apply only to façades facing US 377 and residential properties for that first data center. Also raises Office/Industrial max height to 80 ft and lot coverage to 70%.

Who should act

  • Developers / site selectors: a data center is allowed by-right within the Office / Industrial Sub-District (derived from a stated entitlement step factor) source
  • Developers / site selectors: after site plans have been submitted for the first data center in the Office / Industrial Sub-district for review and approval, that each successive data center thereafter shall require a specific use permit (derived from a stated conditions factor) source
  • Developers / site selectors / Investors / lenders / analysts: site plan approval (subject to review and approval by the Planning and Zoning Commission) is required prior to the issuance of development permits and building permits (derived from a stated entitlement step factor) source
  • Developers / site selectors / Investors / lenders / analysts / Equipment / construction suppliers: a development agreement is also required ... grading permits and building permits may not be issued until the development agreement has been reviewed and approved by the Town Council (derived from a stated entitlement step factor) source

What to do next

  • Monitor: site plan approval (subject to review and approval by the Planning and Zoning Commission) is required prior to the issuance of development permits and building permits — Westlake Planning and Zoning Commission [site plan], date not stated (expected) source
  • Monitor: a development agreement ... reviewed and approved by the Town Council — Westlake Town Council [development agreement], date not stated (expected) source

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Circle T Data Center Campus — Circle T Ranch

MunicipalityWestlake
CountyTarrant
Address / locationNortheast corner of US Highway 377 and Westport Parkway, Westlake, TX (PD 3-8, Office/Industrial Sub-District); developer's deck gives 13572 N Main Street, Westlake, TX 76262
DeveloperCircle T Owner, LP
ApplicantKimley-Horn
OwnerCircle T Owner, LP
Source published2026-08-05
Meeting date2026-08-04
First observed by us2026-09-09
Stageapproved
Decided byWestlake Planning & Zoning Commission (site plan, with three added conditions)
IT load (MW)Unknown
Stated capacity figures
  • 300 MW — campus utility capacity (p.6; also 'PH Circle T [300 MW]' on the portfolio map p.3): CAPACITY / UTILITY PROVIDER 300 MW / Oncorsource
  • 350 MW — substation (p.3; also the FAQ web page and white paper p.2 ('dropping a 350-megawatt substation near the pump station'); the substation itself needs its own future site plan (P&Z packet p.41)): A new 350-megawatt substation … Paid for entirely by the developersource
EquipmentUnknown
ApprovalsSite plan for a data center on ~87.96 acres at the NE corner of US 377 and Westport Pkwy, PD 3-8. Staff: substantially complies with the UDC and PD 3-8; recommends approval. P&Z approved with three conditions: 8-ft berm or sound wall on the south line; acoustic barriers/louvers around HVAC, cooling towers and generators; more evergreen/hardwood screening. Four buildings, private substation and backup generators (substation/switchyard excluded from this approval).
Supplier selectionUnknown

Source: https://www.westlake-tx.org/m/newsflash/home/detail/822 — News flash 822 (whole); conditions enumerated in paragraph 5

Not yet established:

  • site-plan application/case number (not in packet text)
  • IT load / critical capacity in MW (only 300 MW utility capacity and a 350 MW substation are stated)
  • tenant identity
  • outcome of the 2026-08-26 Tarrant County hearing, the cause number and the plaintiff
  • whether the development agreement has since been voted on (nothing after 2026-08-18 found)
  • P&Z 2026-08-04 minutes (not yet published on CivicClerk at retrieval time)
  • council vote count on Ordinance 1015 (2025-01-06 minutes are a scanned image; OCR not run)
  • the applicant for the 2024–25 PD 3-8 text amendment (unnamed in the packet text)
  • equipment vendors / supplier selection (only Ameristar Palisade fence and Lueders stone, presentation pp.18–22)
  • The vote itself is known from the Town's recap and the later resolution recital, not from minutes — the P&Z minutes for 2026-08-04 were not in the events returned (no 'Minutes' file on that event yet).
  • A site-plan approval, not a use decision and not the development agreement.

Our review

Review stateneeds_review

Inference

Unknown

Why it matters

  • capacity power — a four-building data center campus that includes a private electrical substation and backup generators source, News flash 822, paragraph 2
  • opposition — several hours of public comment from neighboring property owners ... concerns about potential noise, visual impacts, and how the project could affect nearby neighborhoods source, News flash 822, paragraphs 1 and 4
  • conditions — the Planning & Zoning Commission requested several additional improvements ... an 8-foot berm or sound barrier wall along the southern property line, additional architectural sound barriers or acoustic louvers around mechanical equipment such as HVAC units, cooling towers, and generators, and more evergreen and hardwood trees source, News flash 822, paragraph 5
  • land — a data center on approximately 87.96 acres of land generally located at the northeast corner of the intersection of United States Highway 377 and Westport Parkway ... in PD, Planned Development District 3-8 source, p.40
  • entitlement step — the switchyard and the sub-station, while shown on the site plan, are not part of the site plan review and approval and will require separate site plans for review and approval by the Planning and Zoning Commission source, p.41
  • schedule — No construction is permitted to take place on the site until the development agreement has been approved by the Town Council source, p.42
  • entitlement step — Under the property's existing Planned Development zoning (PD-3-8), data centers are already permitted on that land ... the commission's responsibility was limited to determining whether the site plan complied source, News flash 822, paragraph 6

Site plan for a data center on ~87.96 acres at the NE corner of US 377 and Westport Pkwy, PD 3-8. Staff: substantially complies with the UDC and PD 3-8; recommends approval. P&Z approved with three conditions: 8-ft berm or sound wall on the south line; acoustic barriers/louvers around HVAC, cooling towers and generators; more evergreen/hardwood screening. Four buildings, private substation and backup generators (substation/switchyard excluded from this approval). Capacity as stated: 300 MW — campus utility capacity (p.6; also 'PH Circle T [300 MW]' on the portfolio map p.3) <https://www.westlake-tx.org/DocumentCenter/View/6805/Data-Center-P-and-Z-Presentation>; 350 MW — substation (p.3; also the FAQ web page and white paper p.2 ('dropping a 350-megawatt substation near the pump station'); the substation itself needs its own future site plan (P&Z packet p.41)) <https://www.westlake-tx.org/DocumentCenter/View/6810/Data-Center-FAQ2>

Who should act

  • Utilities / infrastructure / Equipment / construction suppliers: a four-building data center campus that includes a private electrical substation and backup generators (derived from a stated capacity power factor) source
  • Public affairs / community: several hours of public comment from neighboring property owners ... concerns about potential noise, visual impacts, and how the project could affect nearby neighborhoods (derived from a stated opposition factor) source
  • Equipment / construction suppliers / Developers / site selectors: the Planning & Zoning Commission requested several additional improvements ... an 8-foot berm or sound barrier wall along the southern property line, additional architectural sound barriers or acoustic louvers around mechanical equipment such as HVAC units, cooling towers, and generators, and more evergreen and hardwood trees (derived from a stated conditions factor) source
  • Developers / site selectors: a data center on approximately 87.96 acres of land generally located at the northeast corner of the intersection of United States Highway 377 and Westport Parkway ... in PD, Planned Development District 3-8 (derived from a stated land factor) source
  • Utilities / infrastructure / Developers / site selectors: the switchyard and the sub-station, while shown on the site plan, are not part of the site plan review and approval and will require separate site plans for review and approval by the Planning and Zoning Commission (derived from a stated entitlement step factor) source
  • Investors / lenders / analysts / Equipment / construction suppliers: No construction is permitted to take place on the site until the development agreement has been approved by the Town Council (derived from a stated schedule factor) source
  • Developers / site selectors / Investors / lenders / analysts: Under the property's existing Planned Development zoning (PD-3-8), data centers are already permitted on that land ... the commission's responsibility was limited to determining whether the site plan complied (derived from a stated entitlement step factor) source

What to do next

  • Monitor: Resolution 26-25 approving a Development Agreement between the Town of Westlake, Texas and Circle T Owner, LP (agenda item E.1, special meeting) — Westlake Town Council [development agreement], 2026-08-17 (scheduled) source
  • Monitor: separate site plans for the switchyard and the sub-station for review and approval by the Planning and Zoning Commission — Westlake Planning and Zoning Commission [site plan], date not stated (expected) source

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Circle T Data Center Campus — Circle T Ranch

MunicipalityWestlake
CountyTarrant
Address / locationNortheast corner of US Highway 377 and Westport Parkway, Westlake, TX (PD 3-8, Office/Industrial Sub-District); developer's deck gives 13572 N Main Street, Westlake, TX 76262
DeveloperCircle T Owner, LP
ApplicantUnknown
OwnerCircle T Owner, LP
Source published2026-08-18
Meeting date2026-08-17
First observed by us2026-09-09
Stageuncertain
Reviewing body (not a final decision)Westlake Town Council (special meeting) — tabled after a Tarrant County judge's temporary hold
IT load (MW)Unknown
Stated capacity figuresUnknown
EquipmentUnknown
ApprovalsResolution 26-25 would approve a Development Agreement for Subdivision Improvements between the Town and Circle T Owner, LP: one-time contribution up to $914,000 for pump-station piping (due within 30 days of execution); cooling system WUE not to exceed 0.25 L/kWh long-term average; acoustic louvers, berms and sound walls plus a noise-compliance report within 180 days of construction completion; PUCT/ERCOT audit documentation under the Governor's 2026-08-03 directive required before a final certificate of occupancy, failing which the Town Manager may require the buildings be repurposed; no grading until Town Engineer approves grading/drainage plans. Council unanimously TABLED it because a Tarrant County judge placed a temporary hold; a court hearing was set for 10 am 2026-08-26 and a vote was to be scheduled afterwards.
Supplier selectionUnknown

Source: https://www.westlake-tx.org/m/newsflash/Home/Detail/825 — News flash 825 (whole)

Not yet established:

  • site-plan application/case number (not in packet text)
  • IT load / critical capacity in MW (only 300 MW utility capacity and a 350 MW substation are stated)
  • tenant identity
  • outcome of the 2026-08-26 Tarrant County hearing, the cause number and the plaintiff
  • whether the development agreement has since been voted on (nothing after 2026-08-18 found)
  • P&Z 2026-08-04 minutes (not yet published on CivicClerk at retrieval time)
  • council vote count on Ordinance 1015 (2025-01-06 minutes are a scanned image; OCR not run)
  • the applicant for the 2024–25 PD 3-8 text amendment (unnamed in the packet text)
  • equipment vendors / supplier selection (only Ameristar Palisade fence and Lueders stone, presentation pp.18–22)
  • Separate track from seq 4: tabling the agreement does not undo the site-plan approval; conversely no building or grading permit can issue until the agreement is approved (P&Z packet p.41–42).
  • The August 26 hearing's outcome, cause number and plaintiff are in no preserved document. CivicClerk shows no council event between 2026-08-18 and 2026-09-01 other than the 08-25 Board of Trustees; the 2026-08-18 regular-meeting recap (826) has no data-center item.
  • Status as of 2026-09-09 is unknown from these sources.

Our review

Review stateneeds_review

Inference

Unknown

Why it matters

  • litigation — a Tarrant County judge put a temporary hold on the project. Because of the court order, the Town Council cannot act on the agreement at this time source, News flash 825, paragraphs 1-2
  • entitlement step — The Office of the Town Manager recommends approval of the development agreement as presented source, p.5
  • conditions — The development agreement --- and the ability of the Developer to receive a certificate of occupancy to operate the data center are predicated upon the Developer's compliance with the directive from the Governor concerning the comprehensive data center audit process that ... will be performed by the Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT) source, pp.3-4
  • conditions — In the event that the Developer is unable to receive the appropriate documentation from the PUCT and ERCOT ... the Town Manager may request that the Developer repurpose the buildings on the site for another land use source, p.4
  • water — cooling system designed to achieve an annual water usage effectiveness (WUE) not to exceed 0.25L/kWh as a long-term average source, p.4
  • conditions — heightened mitigation efforts for noise reduction ... acoustic louvers, berms, and sound barrier walls ... a report within 180 days following the completion of construction that demonstrates that the development is compliant with the Town's Code of Ordinances regulating noise source, p.4
  • One-time financial contribution — a one-time financial contribution to the Town in an amount not to exceed $914,000.00 to upgrade piping at the pump station ... to be paid to the Town within 30 calendar days of the execution of the development agreement source, pp.4-5
  • schedule — no grading activities will be allowed to commence unless and until the grading plans and drainage plans have been reviewed and approved by the Town Engineer source, p.4

Resolution 26-25 would approve a Development Agreement for Subdivision Improvements between the Town and Circle T Owner, LP: one-time contribution up to $914,000 for pump-station piping (due within 30 days of execution); cooling system WUE not to exceed 0.25 L/kWh long-term average; acoustic louvers, berms and sound walls plus a noise-compliance report within 180 days of construction completion; PUCT/ERCOT audit documentation under the Governor's 2026-08-03 directive required before a final certificate of occupancy, failing which the Town Manager may require the buildings be repurposed; no grading until Town Engineer approves grading/drainage plans. Council unanimously TABLED it because a Tarrant County judge placed a temporary hold; a court hearing was set for 10 am 2026-08-26 and a vote was to be scheduled afterwards.

Who should act

  • Investors / lenders / analysts / Developers / site selectors / Public affairs / community: a Tarrant County judge put a temporary hold on the project. Because of the court order, the Town Council cannot act on the agreement at this time (derived from a stated litigation factor) source
  • Developers / site selectors / Investors / lenders / analysts: The Office of the Town Manager recommends approval of the development agreement as presented (derived from a stated entitlement step factor) source
  • Investors / lenders / analysts / Utilities / infrastructure: The development agreement --- and the ability of the Developer to receive a certificate of occupancy to operate the data center are predicated upon the Developer's compliance with the directive from the Governor concerning the comprehensive data center audit process that ... will be performed by the Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT) (derived from a stated conditions factor) source
  • Investors / lenders / analysts: In the event that the Developer is unable to receive the appropriate documentation from the PUCT and ERCOT ... the Town Manager may request that the Developer repurpose the buildings on the site for another land use (derived from a stated conditions factor) source
  • Utilities / infrastructure / Equipment / construction suppliers / Public affairs / community: cooling system designed to achieve an annual water usage effectiveness (WUE) not to exceed 0.25L/kWh as a long-term average (derived from a stated water factor) source
  • Equipment / construction suppliers / Public affairs / community: heightened mitigation efforts for noise reduction ... acoustic louvers, berms, and sound barrier walls ... a report within 180 days following the completion of construction that demonstrates that the development is compliant with the Town's Code of Ordinances regulating noise (derived from a stated conditions factor) source
  • Investors / lenders / analysts / Utilities / infrastructure: a one-time financial contribution to the Town in an amount not to exceed $914,000.00 to upgrade piping at the pump station ... to be paid to the Town within 30 calendar days of the execution of the development agreement (derived from a stated other factor) source
  • Equipment / construction suppliers: no grading activities will be allowed to commence unless and until the grading plans and drainage plans have been reviewed and approved by the Town Engineer (derived from a stated schedule factor) source

What to do next

  • Monitor: A Tarrant County judge is expected to hear the matter at a hearing set for 10 am on August 26th — Tarrant County district court, 2026-08-26 (scheduled) source
  • Monitor: Afterward, the Town will schedule a meeting to vote on the development agreement — Westlake Town Council [development agreement], date not stated (expected) source

Garland, TX — Z 23-47, Prime Data Centers (2024)

3 records, 6 hashed source documents. Garland, TX — Z 23-47, Prime Data Centers / Munsch Hardt Kopf & Harr, 2000 Holford Road (District 7). Source-backed, historical_backfill fixture for the Data Center section (Z-DC-18 / I-02, second municipal path). Retrieved 2026-09-10 by the integration writer through the CivicClerk API the collector uses (tenant garlandtx); raw documents and per-page text live outside the repo (data/sources/garla…

As the weekly brief lists them

Reporting period: 2026-09-10 to 2026-09-10. 1 project with newly observed or changed records (3 records) in this period.

Coverage: UNVERIFIED — prototype fixtures only; no live monitoring occurred.

  • SAMPLE: fixture records rendered for inspection; not a live reporting window

Executive summary

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Prime Data Centers — 2000 Holford Road (Z 23-47)

2024-04-02 — Garland City Council — Ordinance No. 7520 adopted (consent item 9.b) · Garland, Dallas County (first observed by us 2026-09-10)

What changed

rezoning_pd: still approved (2024-04-02; previously 2024-03-19). approved — Garland City Council — Ordinance No. 7520 adopted (consent item 9.b), 2024-04-02; 891 days since this action

Why it matters

  • entitlement step — Ordinance No. 7520 ... approving a Change in Zoning from Agricultural (AG) District to a Planned Development (PD) District based in the Community Office (CO) District and 2) a Detail Plan for a Data Center and Electric Substations on a 48.93-acre tract of land located at 2000 Holford Road source, p.4
  • capacity power — 48MW DATA CENTER -- one label on each of the three Detail Plan buildings DFW02-01, DFW02-02, DFW02-03 (Exhibits C-E) source, pp.194, 195, 197
  • capacity power (implied) — SUBSTATION / ONCOR / 75' ONCOR EASEMENT shown on the Detail Plan source, p.194
  • conditions — The purpose of this Planned Development is to approve a Data Center and Electric Substations source, p.191 (Exhibit B)

Ordinance No. 7520 adopted 2024-04-02: a Change in Zoning from AG to a PD based in CO and a Detail Plan for a Data Center and Electric Substations on 48.93 acres at 2000 Holford Road; PD conditions (Exhibit B) permit CO uses plus a Data Center Use and an Electric Substation Use, with the landscape and screening plan (8-ft ornamental fence at the data center, 8-ft solid wall at the substation). Capacity as stated: 48 MW — type not stated (Detail Plan sheets pp.194, 195, 197 (Exhibits C–E; one label per building; three buildings)), per building × 3; campus total not stated <https://garlandtx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=285,plainText=false)>

Who should act

  • Developers / site selectors / Investors / lenders / analysts: Ordinance No. 7520 ... approving a Change in Zoning from Agricultural (AG) District to a Planned Development (PD) District based in the Community Office (CO) District and 2) a Detail Plan for a Data Center and Electric Substations on a 48.93-acre tract of land located at 2000 Holford Road (derived from a stated entitlement step factor) source
  • Utilities / infrastructure / Investors / lenders / analysts: 48MW DATA CENTER -- one label on each of the three Detail Plan buildings DFW02-01, DFW02-02, DFW02-03 (Exhibits C-E) (derived from a stated capacity power factor) source
  • Utilities / infrastructure: SUBSTATION / ONCOR / 75' ONCOR EASEMENT shown on the Detail Plan (derived from an implied capacity power factor) source
  • Developers / site selectors: The purpose of this Planned Development is to approve a Data Center and Electric Substations (derived from a stated conditions factor) source

What to do next

no dated next step in the sources

Sources

Outcome: https://garlandtx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=1079,plainText=false) — p.4: 'APPROVED Z 23-47 … Ordinance No. 7520'; Packet: https://garlandtx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=285,plainText=false) — item 9.b p.3; staff report p.186; ordinance pp.187–189; Exhibit A p.190

Our analysis

Lifecycle: entitlement approved

how this was derived

rezoning_pd: approved (2024-04-02)

Momentum: unknown

how this was derived

0 dated action(s) in the last 365 d; two are needed

thresholds (provisional): advancing ≤ 90 d, stalled after 180 d, lookback 365 d

Stated risk: none stated

how this was derived

entitlement_step (stated, advances): Ordinance No. 7520 ... approving a Change in Zoning from Agricultural (AG) District to a Planned Development (PD) District based in the Community Office (CO) District and 2) a Detail Plan for a Data Center and Electric Substations on a 48.93-acre tract of land located at 2000 Holford Road

capacity_power (stated, neutral): 48MW DATA CENTER -- one label on each of the three Detail Plan buildings DFW02-01, DFW02-02, DFW02-03 (Exhibits C-E)

capacity_power (implied, neutral): SUBSTATION / ONCOR / 75' ONCOR EASEMENT shown on the Detail Plan

conditions (stated, neutral): The purpose of this Planned Development is to approve a Data Center and Electric Substations

Evidence grade: A (A: an outcome source; B: packet or agenda only; C: corroboration only)

Still unknown

  • IT load / critical capacity: the Detail Plan sheets label each of three buildings '2 STORY 48MW DATA CENTER' (fileId 842 pp.24–27; fileId 285 pp.194–197) without saying what the 48 MW is — recorded as unspecified capacity claims; no IT, critical, utility or substation figure is stated
  • tenant identity (three tenants are mentioned, none named)
  • applicant and owner: the agenda titles, ordinance caption and minutes treat 'Prime Data Centers / Munsch Hardt Kopf & Harr' as the requesting party, while the staff report's role labels (fileId 842 p.17) read 'APPLICANT Woodlands of Spring Creek LP' and 'OWNER Prime Data Centers / Munsch Hardt Kopf & Harr'; no source assigns both roles consistently
  • construction, site-plan or later amendments after 2024-04-16 (not checked)

Timeline

3 dated records of this project in the period; the current state above is the latest.

  1. 2024-02-26 — proposal — Garland Plan Commission (recommendation only, 5-3; recommended limiting the PD to the data center and substation)
  2. 2024-03-19 — approved — Garland City Council — public hearing, 7 ayes / 2 nays (Lucht, Dutton)
  3. 2024-04-02 — approved — Garland City Council — Ordinance No. 7520 adopted (consent item 9.b) (current)

Timeline

  1. 2024-02-26 — proposal · Garland Plan Commission (recommendation only, 5-3; recommended limiting the PD to the data center and substation) · record
  2. 2024-03-19 — approved · Garland City Council — public hearing, 7 ayes / 2 nays (Lucht, Dutton) · record
  3. 2024-04-02 — approved · Garland City Council — Ordinance No. 7520 adopted (consent item 9.b) · record

Evidence cards

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Prime Data Centers — 2000 Holford Road (Z 23-47)

MunicipalityGarland
CountyDallas
Address / location2000 Holford Road, Garland, TX (District 7); a 48.93-acre tract, Lot 2, Block 1, Sanctuary Addition (Ordinance Exhibit A)
DeveloperUnknown
ApplicantUnknown
OwnerUnknown
Source publishedUnknown
Meeting date2024-02-26
First observed by us2026-09-10
Stageproposal
Reviewing body (not a final decision)Garland Plan Commission (recommendation only, 5-3; recommended limiting the PD to the data center and substation)
IT load (MW)Unknown
Stated capacity figures
  • 48 MW — type not stated (Detail Plan sheets pp.24, 25, 27 (one label per building; three buildings)): DFW02-01 2 STORY 48MW DATA CENTER 710' x 194' FFE: 546.00'source
  • 48 MW — type not stated (Detail Plan sheets pp.24, 25, 27 (one label per building; three buildings)): DFW02-02 2 STORY 48MW DATA CENTER 710' x 194' FFE: 546.00'source
  • 48 MW — type not stated (Detail Plan sheets pp.24, 25, 27 (one label per building; three buildings)): DFW02-03 2 STORY 48MW DATA CENTER 710' x 194' FFE: 546.00'source
EquipmentUnknown
ApprovalsStaff recommended approval (planning report, fileId 842 pp.17–19). Plan Commission public hearing 2024-02-26: motion to approve as presented, with the recommendation that the PD be permitted only for the data center and substation, carried 5–3.
Supplier selectionUnknown

Source: https://garlandtx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=835,plainText=false) — 2024-03-11 packet pp.5–7 (2024-02-26 minutes, item 3.a)

Not yet established:

  • IT load / critical capacity: the Detail Plan sheets label each of three buildings '2 STORY 48MW DATA CENTER' (fileId 842 pp.24–27; fileId 285 pp.194–197) without saying what the 48 MW is — recorded as unspecified capacity claims; no IT, critical, utility or substation figure is stated
  • tenant identity (three tenants are mentioned, none named)
  • applicant and owner: the agenda titles, ordinance caption and minutes treat 'Prime Data Centers / Munsch Hardt Kopf & Harr' as the requesting party, while the staff report's role labels (fileId 842 p.17) read 'APPLICANT Woodlands of Spring Creek LP' and 'OWNER Prime Data Centers / Munsch Hardt Kopf & Harr'; no source assigns both roles consistently
  • equipment vendors / supplier selection (none stated)
  • A recommendation, not a decision (regression c).

Our review

Review stateneeds_review

Inference

Unknown

Why it matters

  • entitlement step — Both data centers and electric substations require a Specific Use Provision in the Community Office (CO) District. The applicant proposes to allow both uses by right through this Planned Development source, p.17
  • capacity power — three (3) electric substations are proposed to support the data center. Two (2) of those substations will be maintained by Oncor and the third substation will be maintained Garland Power & Light (GP&L) source, p.17
  • capacity power — the buildings will be dual fed by two different electric companies, the generators will only be activated if there is a total power outage or during load testing source, p.6
  • land — The overall site consists of approximately 48.93 acres with approximately 1,426 lineal feet of frontage along Holford Road source, p.17
  • tenant — the tenant will be a cloud-based company that would cover companies in and around the DFW market source, p.6
  • schedule — The current plan is to build the first two buildings at the same time and have them come online about three months apart ... The approximate construction time for the entire project is 24 months source, p.6
  • opposition — Resident speaking in opposition ... expressed concern that an industrial area is being moved into a residential area source, p.7
  • conditions — an eight (8)-foot ornamental metal fence around the data center and an eight (8) - foot solid wall around the electric substation source, p.18
  • Economic Development Strategic Plan — Per the adopted Economic Development Strategic Plan, data centers generate the most revenue per acre by building type source, p.18

Staff recommended approval (planning report, fileId 842 pp.17–19). Plan Commission public hearing 2024-02-26: motion to approve as presented, with the recommendation that the PD be permitted only for the data center and substation, carried 5–3. Capacity as stated: 48 MW — type not stated (Detail Plan sheets pp.24, 25, 27 (one label per building; three buildings)), per building × 3; campus total not stated <https://garlandtx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=842,plainText=false)>

Who should act

  • Developers / site selectors: Both data centers and electric substations require a Specific Use Provision in the Community Office (CO) District. The applicant proposes to allow both uses by right through this Planned Development (derived from a stated entitlement step factor) source
  • Utilities / infrastructure: three (3) electric substations are proposed to support the data center. Two (2) of those substations will be maintained by Oncor and the third substation will be maintained Garland Power & Light (GP&L) (derived from a stated capacity power factor) source
  • Utilities / infrastructure / Equipment / construction suppliers: the buildings will be dual fed by two different electric companies, the generators will only be activated if there is a total power outage or during load testing (derived from a stated capacity power factor) source
  • Developers / site selectors: The overall site consists of approximately 48.93 acres with approximately 1,426 lineal feet of frontage along Holford Road (derived from a stated land factor) source
  • Investors / lenders / analysts: the tenant will be a cloud-based company that would cover companies in and around the DFW market (derived from a stated tenant factor) source
  • Equipment / construction suppliers / Investors / lenders / analysts: The current plan is to build the first two buildings at the same time and have them come online about three months apart ... The approximate construction time for the entire project is 24 months (derived from a stated schedule factor) source
  • Public affairs / community: Resident speaking in opposition ... expressed concern that an industrial area is being moved into a residential area (derived from a stated opposition factor) source
  • Equipment / construction suppliers: an eight (8)-foot ornamental metal fence around the data center and an eight (8) - foot solid wall around the electric substation (derived from a stated conditions factor) source
  • Public affairs / community / Investors / lenders / analysts: Per the adopted Economic Development Strategic Plan, data centers generate the most revenue per acre by building type (derived from a stated other factor) source

What to do next

  • Monitor: CITY COUNCIL DATE: March 19, 2024 (Z 23-47 public hearing) — Garland City Council [rezoning pd], 2024-03-19 (scheduled) source

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Prime Data Centers — 2000 Holford Road (Z 23-47)

MunicipalityGarland
CountyDallas
Address / location2000 Holford Road, Garland, TX (District 7); a 48.93-acre tract, Lot 2, Block 1, Sanctuary Addition (Ordinance Exhibit A)
DeveloperUnknown
ApplicantUnknown
OwnerUnknown
Source publishedUnknown
Meeting date2024-03-19
First observed by us2026-09-10
Stageapproved
Decided byGarland City Council — public hearing, 7 ayes / 2 nays (Lucht, Dutton)
IT load (MW)Unknown
Stated capacity figuresUnknown
EquipmentUnknown
ApprovalsPublic hearing 2024-03-19: motion to approve the change in zoning to a PD based in CO and the Detail Plan for a Data Center and Electric Substations carried 7 ayes, 2 nays; discussion of proximity to the Spring Creek Preserve.
Supplier selectionUnknown

Source: https://garlandtx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=291,plainText=false) — 2024-03-19 minutes p.6, item b

Not yet established:

  • IT load / critical capacity: the Detail Plan sheets label each of three buildings '2 STORY 48MW DATA CENTER' (fileId 842 pp.24–27; fileId 285 pp.194–197) without saying what the 48 MW is — recorded as unspecified capacity claims; no IT, critical, utility or substation figure is stated
  • tenant identity (three tenants are mentioned, none named)
  • applicant and owner: the agenda titles, ordinance caption and minutes treat 'Prime Data Centers / Munsch Hardt Kopf & Harr' as the requesting party, while the staff report's role labels (fileId 842 p.17) read 'APPLICANT Woodlands of Spring Creek LP' and 'OWNER Prime Data Centers / Munsch Hardt Kopf & Harr'; no source assigns both roles consistently
  • the 2024-03-19 agenda packet (fileId 290) was not fetched

Our review

Review stateneeds_review

Inference

Unknown

Why it matters

  • land — There was discussion among the Council and applicants regarding the location of the proposed project and the proximity to the Spring Creek Preserve source, p.6
  • entitlement step — Case Z 23-47 was approved via public hearing during the March 19, 2024 Regular City Council meeting ... Consider adoption of the attached ordinance source, p.186

Public hearing 2024-03-19: motion to approve the change in zoning to a PD based in CO and the Detail Plan for a Data Center and Electric Substations carried 7 ayes, 2 nays; discussion of proximity to the Spring Creek Preserve.

Who should act

  • Public affairs / community / Developers / site selectors: There was discussion among the Council and applicants regarding the location of the proposed project and the proximity to the Spring Creek Preserve (derived from a stated land factor) source
  • Developers / site selectors / Investors / lenders / analysts: Case Z 23-47 was approved via public hearing during the March 19, 2024 Regular City Council meeting ... Consider adoption of the attached ordinance (derived from a stated entitlement step factor) source

What to do next

  • Monitor: Z 23-47 Prime Data Centers/Munsch Hardt Kopf & Harr -- consider adoption of the attached ordinance (agenda item 9.b) — Garland City Council [rezoning pd], 2024-04-02 (scheduled) source

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Prime Data Centers — 2000 Holford Road (Z 23-47)

MunicipalityGarland
CountyDallas
Address / location2000 Holford Road, Garland, TX (District 7); a 48.93-acre tract, Lot 2, Block 1, Sanctuary Addition (Ordinance Exhibit A)
DeveloperUnknown
ApplicantUnknown
OwnerUnknown
Source publishedUnknown
Meeting date2024-04-02
First observed by us2026-09-10
Stageapproved
Decided byGarland City Council — Ordinance No. 7520 adopted (consent item 9.b)
IT load (MW)Unknown
Stated capacity figures
  • 48 MW — type not stated (Detail Plan sheets pp.194, 195, 197 (Exhibits C–E; one label per building; three buildings)): DFW02-01 2 STORY 48MW DATA CENTER 710' x 194' FFE: 546.00'source
  • 48 MW — type not stated (Detail Plan sheets pp.194, 195, 197 (Exhibits C–E; one label per building; three buildings)): DFW02-02 2 STORY 48MW DATA CENTER 710' x 194' FFE: 546.00'source
  • 48 MW — type not stated (Detail Plan sheets pp.194, 195, 197 (Exhibits C–E; one label per building; three buildings)): DFW02-03 2 STORY 48MW DATA CENTER 710' x 194' FFE: 546.00'source
EquipmentUnknown
ApprovalsOrdinance No. 7520 adopted 2024-04-02: a Change in Zoning from AG to a PD based in CO and a Detail Plan for a Data Center and Electric Substations on 48.93 acres at 2000 Holford Road; PD conditions (Exhibit B) permit CO uses plus a Data Center Use and an Electric Substation Use, with the landscape and screening plan (8-ft ornamental fence at the data center, 8-ft solid wall at the substation).
Supplier selectionUnknown

Source: https://garlandtx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=1079,plainText=false) — 2024-04-02 minutes p.4, item b

Not yet established:

  • IT load / critical capacity: the Detail Plan sheets label each of three buildings '2 STORY 48MW DATA CENTER' (fileId 842 pp.24–27; fileId 285 pp.194–197) without saying what the 48 MW is — recorded as unspecified capacity claims; no IT, critical, utility or substation figure is stated
  • tenant identity (three tenants are mentioned, none named)
  • applicant and owner: the agenda titles, ordinance caption and minutes treat 'Prime Data Centers / Munsch Hardt Kopf & Harr' as the requesting party, while the staff report's role labels (fileId 842 p.17) read 'APPLICANT Woodlands of Spring Creek LP' and 'OWNER Prime Data Centers / Munsch Hardt Kopf & Harr'; no source assigns both roles consistently
  • construction, site-plan or later amendments after 2024-04-16 (not checked)

Our review

Review stateneeds_review

Inference

Unknown

Why it matters

  • entitlement step — Ordinance No. 7520 ... approving a Change in Zoning from Agricultural (AG) District to a Planned Development (PD) District based in the Community Office (CO) District and 2) a Detail Plan for a Data Center and Electric Substations on a 48.93-acre tract of land located at 2000 Holford Road source, p.4
  • capacity power — 48MW DATA CENTER -- one label on each of the three Detail Plan buildings DFW02-01, DFW02-02, DFW02-03 (Exhibits C-E) source, pp.194, 195, 197
  • capacity power (implied) — SUBSTATION / ONCOR / 75' ONCOR EASEMENT shown on the Detail Plan source, p.194
  • conditions — The purpose of this Planned Development is to approve a Data Center and Electric Substations source, p.191 (Exhibit B)

Ordinance No. 7520 adopted 2024-04-02: a Change in Zoning from AG to a PD based in CO and a Detail Plan for a Data Center and Electric Substations on 48.93 acres at 2000 Holford Road; PD conditions (Exhibit B) permit CO uses plus a Data Center Use and an Electric Substation Use, with the landscape and screening plan (8-ft ornamental fence at the data center, 8-ft solid wall at the substation). Capacity as stated: 48 MW — type not stated (Detail Plan sheets pp.194, 195, 197 (Exhibits C–E; one label per building; three buildings)), per building × 3; campus total not stated <https://garlandtx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=285,plainText=false)>

Who should act

  • Developers / site selectors / Investors / lenders / analysts: Ordinance No. 7520 ... approving a Change in Zoning from Agricultural (AG) District to a Planned Development (PD) District based in the Community Office (CO) District and 2) a Detail Plan for a Data Center and Electric Substations on a 48.93-acre tract of land located at 2000 Holford Road (derived from a stated entitlement step factor) source
  • Utilities / infrastructure / Investors / lenders / analysts: 48MW DATA CENTER -- one label on each of the three Detail Plan buildings DFW02-01, DFW02-02, DFW02-03 (Exhibits C-E) (derived from a stated capacity power factor) source
  • Utilities / infrastructure: SUBSTATION / ONCOR / 75' ONCOR EASEMENT shown on the Detail Plan (derived from an implied capacity power factor) source
  • Developers / site selectors: The purpose of this Planned Development is to approve a Data Center and Electric Substations (derived from a stated conditions factor) source

What to do next

no dated next step in the sources

Prosper, TX — ZONE-26-0007, Project Tomahawk (2026, outcome unknown)

1 record, 4 hashed source documents. Prosper, TX — ZONE-26-0007, 'Project Tomahawk', a Planned Development for a Data Center on 37.3 acres south of Parvin Road east of FM 1385. Source-backed, historical_backfill SAMPLE record for the Data Center section (Z-DC-18, third municipal path; assembled 2026-09-10 by the read-only support session from the Town's own Municode Meetings hub, the seeded platform for Prosper). Raw documents live o…

As the weekly brief lists them

Reporting period: 2026-09-10 to 2026-09-10. 1 newly observed or changed project record in this period.

Coverage: UNVERIFIED — prototype fixtures only; no live monitoring occurred.

  • SAMPLE: fixture records rendered for inspection; not a live reporting window

Executive summary

  • Project Tomahawk — Parvin Road at FM 1385 (ZONE-26-0007) (Prosper) — new track: rezoning_pd recommended_approval (2026-09-01) — Prosper Planning and Zoning Commission — public hearing 2026-09-01; Town Staff recommended approval; next: Conduct a Public Hearing and consider and act upon a request for a rezoning from Agricultural to a Planned Development for a Data Center ... (ZONE-26-0007), agenda item 4 2026-09-01 (past)

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Project Tomahawk — Parvin Road at FM 1385 (ZONE-26-0007)

2026-09-01 — Prosper Planning and Zoning Commission — public hearing 2026-09-01; Town Staff recommended approval · Prosper, Denton County (first observed by us 2026-09-10)

What changed

new track: rezoning_pd recommended_approval (2026-09-01). proposal — Prosper Planning and Zoning Commission — public hearing 2026-09-01; Town Staff recommended approval, 2026-09-01; 9 days since this action

Why it matters

  • entitlement step — Town Staff recommends the Planning and Zoning Commission approve the request for a rezoning from Agricultural to a Planned Development for a Data Center source, p.49
  • opposition — Town Staff has received 34 letters of opposition, 11 from Prosper residents, and one letter of support to the proposed zoning request to date source, p.49
  • land — a Planned Development for a Data Center on a portion of Parvin 1385 Addition, Block A, Lot 2, on 37.3 acres, located 1,590 feet south of Parvin Road and 855 feet east of FM 1385 ... The facility will cover 20 percent of the lot source, p.45
  • entitlement step — A request to modify the Future Land Use Plan has been submitted as a companion case to this item source, p.45
  • capacity power (implied) — located behind ... the Brazos substation that fronts FM 1385 source, p.45
  • capacity power — The proposed development will be responsible for all upgrades needed for power consumption source, p.48
  • water — The proposed development will consume less than half of the water used in a single-family home source, p.48
  • conditions — an eight-foot masonry wall will be installed at the rear of the building to both screen and provide a sound-dampening mechanism for the generators source, p.48
  • conditions — Decibel Level Range: 41.7 - 55 dB(A) (proposed data center) versus 59.7 - 70.8 dB(A) (current vacant site) source, p.49
  • entitlement step — Attached Documents: ... 13. Draft Development Agreement source, p.49

Requested: rezoning from Agricultural to a Planned Development for a Data Center on 37.3± acres (ZONE-26-0007) with a companion Future Land Use Plan amendment from Medium Density Residential and Retail and Neighborhood Services to Business Park; a draft Development Agreement (DEVAGRE-26-0011) is attached. Staff recommendation: approve. No decision by the commission or the council appears in any fetched document.

Who should act

  • Developers / site selectors / Investors / lenders / analysts: Town Staff recommends the Planning and Zoning Commission approve the request for a rezoning from Agricultural to a Planned Development for a Data Center (derived from a stated entitlement step factor) source
  • Public affairs / community / Investors / lenders / analysts: Town Staff has received 34 letters of opposition, 11 from Prosper residents, and one letter of support to the proposed zoning request to date (derived from a stated opposition factor) source
  • Developers / site selectors: a Planned Development for a Data Center on a portion of Parvin 1385 Addition, Block A, Lot 2, on 37.3 acres, located 1,590 feet south of Parvin Road and 855 feet east of FM 1385 ... The facility will cover 20 percent of the lot (derived from a stated land factor) source
  • Developers / site selectors: A request to modify the Future Land Use Plan has been submitted as a companion case to this item (derived from a stated entitlement step factor) source
  • Utilities / infrastructure: located behind ... the Brazos substation that fronts FM 1385 (derived from an implied capacity power factor) source
  • Utilities / infrastructure / Investors / lenders / analysts: The proposed development will be responsible for all upgrades needed for power consumption (derived from a stated capacity power factor) source
  • Utilities / infrastructure / Public affairs / community: The proposed development will consume less than half of the water used in a single-family home (derived from a stated water factor) source
  • Equipment / construction suppliers / Public affairs / community: an eight-foot masonry wall will be installed at the rear of the building to both screen and provide a sound-dampening mechanism for the generators (derived from a stated conditions factor) source
  • Public affairs / community / Equipment / construction suppliers: Decibel Level Range: 41.7 - 55 dB(A) (proposed data center) versus 59.7 - 70.8 dB(A) (current vacant site) (derived from a stated conditions factor) source
  • Developers / site selectors / Investors / lenders / analysts: Attached Documents: ... 13. Draft Development Agreement (derived from a stated entitlement step factor) source

What to do next

  • Look up: Conduct a Public Hearing and consider and act upon a request for a rezoning from Agricultural to a Planned Development for a Data Center ... (ZONE-26-0007), agenda item 4 — Prosper Planning and Zoning Commission [rezoning pd], 2026-09-01 (past — outcome not in the sources) source
  • Look up: Conduct a Public Hearing and consider and act upon a request for a rezoning ... (ZONE-26-0007), agenda item 19 — Prosper Town Council [rezoning pd], 2026-09-08 (past — outcome not in the sources) source
  • Look up: Conduct a Public Hearing and consider and act upon a request to amend the Future Land Use Plan from Medium Density Residential and Retail and Neighborhood Services to Business Park (COMP-26-0001), agenda item 20 — Prosper Town Council [comprehensive plan amendment], 2026-09-08 (past — outcome not in the sources) source
  • Monitor: Draft Development Agreement (attached document 13) [development agreement], date not stated (expected) source

Sources

Packet: https://mccmeetings.blob.core.usgovcloudapi.net/prospertx-pubu/MEET-Packet-74ba703b04e946dc952f6782be3a6bb2.pdf — pp.45–49: 'Re: Planned Development for Project Tomahawk' … 'Town Staff recommends the Planning and Zoning Commission approve the request'; Corroboration: https://mccmeetings.blob.core.usgovcloudapi.net/prospertx-pubu/MEET-Agenda-74ba703b04e946dc952f6782be3a6bb2.pdf — p.2 item 4 (ZONE-26-0007); Corroboration: https://mccmeetings.blob.core.usgovcloudapi.net/prospertx-pubu/MEET-Agenda-31cdf54f8aaf426b875fa67f524bf692.pdf — Town Council 2026-09-08 agenda p.3 item 19 (hearing scheduled)

Our analysis

Lifecycle: entitlement pending

how this was derived

rezoning_pd: recommended_approval (2026-09-01)

Momentum: unknown

how this was derived

1 dated action(s) in the last 365 d; two are needed

thresholds (provisional): advancing ≤ 90 d, stalled after 180 d, lookback 365 d

Stated risk: stated

how this was derived

entitlement_step (stated, advances): Town Staff recommends the Planning and Zoning Commission approve the request for a rezoning from Agricultural to a Planned Development for a Data Center

opposition (stated, impedes): Town Staff has received 34 letters of opposition, 11 from Prosper residents, and one letter of support to the proposed zoning request to date

land (stated, neutral): a Planned Development for a Data Center on a portion of Parvin 1385 Addition, Block A, Lot 2, on 37.3 acres, located 1,590 feet south of Parvin Road and 855 feet east of FM 1385 ... The facility will cover 20 percent of the lot

entitlement_step (stated, neutral): A request to modify the Future Land Use Plan has been submitted as a companion case to this item

capacity_power (implied, neutral): located behind ... the Brazos substation that fronts FM 1385

capacity_power (stated, neutral): The proposed development will be responsible for all upgrades needed for power consumption

water (stated, advances): The proposed development will consume less than half of the water used in a single-family home

conditions (stated, neutral): an eight-foot masonry wall will be installed at the rear of the building to both screen and provide a sound-dampening mechanism for the generators

conditions (stated, advances): Decibel Level Range: 41.7 - 55 dB(A) (proposed data center) versus 59.7 - 70.8 dB(A) (current vacant site)

entitlement_step (stated, neutral): Attached Documents: ... 13. Draft Development Agreement

Evidence grade: B (A: an outcome source; B: packet or agenda only; C: corroboration only)

Still unknown

  • IT load / critical capacity: no megawatt, kilovolt or square-footage figure for the facility appears in the agenda or the 104-page packet; only the tract (37.273 acres) and 20 percent lot coverage are stated
  • the commission's action on 2026-09-01: press reports a 7–0 recommendation of denial; not in any fetched document
  • the council's action on 2026-09-08: press reports the request was withdrawn before the meeting; the agenda only shows the hearing scheduled
  • applicant: no fetched document names the applicant party; press names White Rose Partners, which appears nowhere in the packet; owner of record D9-1 Assets, LLC per the deed cited in Exhibit A-1 and the Exhibit F-1 title block
  • county: the site is in Denton County per the deed and exhibit title block, while the municipality seed row lists Prosper under Collin

Timeline

  1. 2026-09-01 — proposal · Prosper Planning and Zoning Commission — public hearing 2026-09-01; Town Staff recommended approval · record

Evidence cards

HISTORICAL/BACKFILL — first observed after the underlying event, not through live monitoring. Current status is established only by the dated next decision and project timeline.

Project Tomahawk — Parvin Road at FM 1385 (ZONE-26-0007)

MunicipalityProsper
CountyDenton
Address / locationa portion of Parvin 1385 Addition, Block A, Lot 2, 37.3± acres, 1,590± feet south of Parvin Road and 855± feet east of FM 1385, Prosper, TX; behind the Brazos substation that fronts FM 1385
DeveloperUnknown
ApplicantUnknown
OwnerD9-1 Assets, LLC
Source publishedUnknown
Meeting date2026-09-01
First observed by us2026-09-10
Stageproposal
Reviewing body (not a final decision)Prosper Planning and Zoning Commission — public hearing 2026-09-01; Town Staff recommended approval
IT load (MW)Unknown
Stated capacity figuresUnknown
EquipmentUnknown
ApprovalsRequested: rezoning from Agricultural to a Planned Development for a Data Center on 37.3± acres (ZONE-26-0007) with a companion Future Land Use Plan amendment from Medium Density Residential and Retail and Neighborhood Services to Business Park; a draft Development Agreement (DEVAGRE-26-0011) is attached. Staff recommendation: approve. No decision by the commission or the council appears in any fetched document.
Supplier selectionUnknown

Source: https://mccmeetings.blob.core.usgovcloudapi.net/prospertx-pubu/MEET-Packet-74ba703b04e946dc952f6782be3a6bb2.pdf — 2026-09-01 P&Z packet pp.45–49 (staff report); agenda p.2 item 4

Not yet established:

  • IT load / critical capacity: no megawatt, kilovolt or square-footage figure for the facility appears in the agenda or the 104-page packet; only the tract (37.273 acres) and 20 percent lot coverage are stated
  • the commission's action on 2026-09-01: press reports a 7–0 recommendation of denial; not in any fetched document
  • the council's action on 2026-09-08: press reports the request was withdrawn before the meeting; the agenda only shows the hearing scheduled
  • applicant: no fetched document names the applicant party; press names White Rose Partners, which appears nowhere in the packet; owner of record D9-1 Assets, LLC per the deed cited in Exhibit A-1 and the Exhibit F-1 title block
  • county: the site is in Denton County per the deed and exhibit title block, while the municipality seed row lists Prosper under Collin

Our review

Review stateneeds_review

Inference

Unknown

Why it matters

  • entitlement step — Town Staff recommends the Planning and Zoning Commission approve the request for a rezoning from Agricultural to a Planned Development for a Data Center source, p.49
  • opposition — Town Staff has received 34 letters of opposition, 11 from Prosper residents, and one letter of support to the proposed zoning request to date source, p.49
  • land — a Planned Development for a Data Center on a portion of Parvin 1385 Addition, Block A, Lot 2, on 37.3 acres, located 1,590 feet south of Parvin Road and 855 feet east of FM 1385 ... The facility will cover 20 percent of the lot source, p.45
  • entitlement step — A request to modify the Future Land Use Plan has been submitted as a companion case to this item source, p.45
  • capacity power (implied) — located behind ... the Brazos substation that fronts FM 1385 source, p.45
  • capacity power — The proposed development will be responsible for all upgrades needed for power consumption source, p.48
  • water — The proposed development will consume less than half of the water used in a single-family home source, p.48
  • conditions — an eight-foot masonry wall will be installed at the rear of the building to both screen and provide a sound-dampening mechanism for the generators source, p.48
  • conditions — Decibel Level Range: 41.7 - 55 dB(A) (proposed data center) versus 59.7 - 70.8 dB(A) (current vacant site) source, p.49
  • entitlement step — Attached Documents: ... 13. Draft Development Agreement source, p.49

Requested: rezoning from Agricultural to a Planned Development for a Data Center on 37.3± acres (ZONE-26-0007) with a companion Future Land Use Plan amendment from Medium Density Residential and Retail and Neighborhood Services to Business Park; a draft Development Agreement (DEVAGRE-26-0011) is attached. Staff recommendation: approve. No decision by the commission or the council appears in any fetched document.

Who should act

  • Developers / site selectors / Investors / lenders / analysts: Town Staff recommends the Planning and Zoning Commission approve the request for a rezoning from Agricultural to a Planned Development for a Data Center (derived from a stated entitlement step factor) source
  • Public affairs / community / Investors / lenders / analysts: Town Staff has received 34 letters of opposition, 11 from Prosper residents, and one letter of support to the proposed zoning request to date (derived from a stated opposition factor) source
  • Developers / site selectors: a Planned Development for a Data Center on a portion of Parvin 1385 Addition, Block A, Lot 2, on 37.3 acres, located 1,590 feet south of Parvin Road and 855 feet east of FM 1385 ... The facility will cover 20 percent of the lot (derived from a stated land factor) source
  • Developers / site selectors: A request to modify the Future Land Use Plan has been submitted as a companion case to this item (derived from a stated entitlement step factor) source
  • Utilities / infrastructure: located behind ... the Brazos substation that fronts FM 1385 (derived from an implied capacity power factor) source
  • Utilities / infrastructure / Investors / lenders / analysts: The proposed development will be responsible for all upgrades needed for power consumption (derived from a stated capacity power factor) source
  • Utilities / infrastructure / Public affairs / community: The proposed development will consume less than half of the water used in a single-family home (derived from a stated water factor) source
  • Equipment / construction suppliers / Public affairs / community: an eight-foot masonry wall will be installed at the rear of the building to both screen and provide a sound-dampening mechanism for the generators (derived from a stated conditions factor) source
  • Public affairs / community / Equipment / construction suppliers: Decibel Level Range: 41.7 - 55 dB(A) (proposed data center) versus 59.7 - 70.8 dB(A) (current vacant site) (derived from a stated conditions factor) source
  • Developers / site selectors / Investors / lenders / analysts: Attached Documents: ... 13. Draft Development Agreement (derived from a stated entitlement step factor) source

What to do next

  • Monitor: Conduct a Public Hearing and consider and act upon a request for a rezoning from Agricultural to a Planned Development for a Data Center ... (ZONE-26-0007), agenda item 4 — Prosper Planning and Zoning Commission [rezoning pd], 2026-09-01 (scheduled) source
  • Monitor: Conduct a Public Hearing and consider and act upon a request for a rezoning ... (ZONE-26-0007), agenda item 19 — Prosper Town Council [rezoning pd], 2026-09-08 (scheduled) source
  • Monitor: Conduct a Public Hearing and consider and act upon a request to amend the Future Land Use Plan from Medium Density Residential and Retail and Neighborhood Services to Business Park (COMP-26-0001), agenda item 20 — Prosper Town Council [comprehensive plan amendment], 2026-09-08 (scheduled) source
  • Monitor: Draft Development Agreement (attached document 13) [development agreement], date not stated (expected) source